KB: Change the lifecycle state for all components in a project at once

A365 A365
Once components are used in a project, it is sensible to change their lifecycle states, for example from Draft to Prototype. All components that have been used in a project can have its states changed in one go in Explorer panel.

Solution Details

Lifecycle states for all components used in a project or project release can be changed in the Children tab of the Explorer panel in Classic View.

  1. View » Panel » Explorer and click the gear icon at the top-right to set to Classic View 
     
    1.jpg

  2. Select the project or project release in the Explorer panel

  3. Multi-select all of the component CMP- items in the Children tab by shift+click the first and last components

  4. Right-click over the selected components and choose "Operations - Change state..." 
    2.jpg

  5. Click Process in the "Batch state change" dialog to transition all of the components to the next lifecycle state  
    3.jpg

 
If you find an issue, select the text/image and pressCtrl + Enterto send us your feedback.